Work Profile Report [23W1224]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/191519/2024 e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.32
Resanction Cost :
29.32
Tentative Cost :
28.25
Saving
1.07
Exp. Upto Last Fy :
12.55
For CFY 2024-2025
Remaining :
16.77
Demand :
14.00
Allotment :
11.81
Exp in CFY :
11.81
Total Up to Date Exp :
24.36
Construction Started
Sanction on : 10 months 4 days ago
20 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 4 months 2 weeks ago
10 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: