Work Profile Report [23W1239]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O. no.- I/230521/2024, e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
193.68
Resanction Cost :
193.68
Tentative Cost :
193.68
Exp. Upto Last Fy :
171.12
For CFY 2025-2026
Remaining :
22.56
Demand :
22.67
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
171.12
Work completed
Sanction on : 8 months 3 weeks ago
06 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 4 weeks ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 05-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand