Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.500 | 0 | 0.000 | 0.000 |
23W989 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4592/।।।(2)/19-66 (एम0एल0ए0)/17 दिनांक 27-12-2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.81
Resanction Cost :
24.81
Tentative Cost :
24.81
Exp. Upto Last Fy : 21.91
For CFY 2024-2025
Remaining : 2.90
Demand : 2.90
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.91
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 6 months ago
27 Dec 2019
Tentative Completion date:
3 years 8 months ago
31 Oct 2020
Actual Completion Date:
1 year 8 months ago
15 Nov 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Dec-2022
Physical Peramenters