Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.500 | 0.000 |
23W990 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4592/।।।(2)/19-66 (एम0एल0ए0)/17 दिनांक 27-12-2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.77
Resanction Cost :
18.77
Tentative Cost :
18.77
Exp. Upto Last Fy : 8.49
For CFY 2024-2025
Remaining : 10.28
Demand : 10.28
Allotment : 0.00
Exp in CFY : 13.46
Total Up to Date Exp : 21.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
4 years 6 months ago
27 Dec 2019
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 20-Jun-2024
Physical Peramenters