Work Profile Report [24W1003]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून का पत्रांक 1390/03 बजट(मार्ग/सेतु-नये कार्य(रा0से0)/2024-25 दि0 20-07-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.43
Resanction Cost :
2.43
Tentative Cost :
2.43
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
2.43
Demand :
2.40
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Alignment Approved
Sanction on : 5 months 4 days ago
20 Jul 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 9 months 3 weeks from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण पूर्ण। -- as on 19-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand