Work Profile Report [24W1006]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाइल सं0 75151 लोक निर्माण अनुभाग - 2 दि0 01-08-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1.48
Resanction Cost :
1.48
Tentative Cost :
1.48
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
1.38
Demand :
1.38
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 8 months 3 weeks ago
01 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 5 months 2 weeks from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य प्रगति पर है। -- as on 11-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand