Work Profile Report [24W1065]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन का ई पत्रावली संख्या 60173 लो0 नि0 अनुभाग -2 देहरादून दिनांक 27-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.52
Resanction Cost :
49.52
Tentative Cost :
49.52
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
49.42
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 4 months 1 week ago
27 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
75 %
Tentative Completion date on : 4 months 3 weeks from now
30 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
तटबन्ध, जी0एस0बी0, जी0-2 का कार्य पूर्ण। जी0-3 का कार्य प्रगति पर है। -- as on 09-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: