Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.3 | 15.3 | 15.300 | 0 | 0.000 | 0.000 |
24W731 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनदेश संख्या 616(1)/।।।(2)/20-68(एम0एल0ए0)/2017 दिनांक 07-02-2020
TS Amount (lakhs) : 2490.31 Lacs
Financial Detail
Sanction Cost : 2,490.31 Lacs
Resanction Cost : 2,490.31 Lacs
Exp. Upto Last Fy : 2,379.08 Lacs
For CFY 2024-2025
Remaining : 111.23 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2,379.08 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 3 months ago
07 Feb 2020
Tentative Completion date:
1 year 11 months ago
31 May 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अनुरक्षण अवधि पर है। पी0सी0सी0 प्रेषित। -- as on 17-Jun-2023
Physical Peramenters