Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.500 | 0 | 0.000 | 0.000 |
24W779 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी उधमसिंह नगर का पत्रांक 693/जि.यो./लो.नि.वि. विभाग /2021-22 दिनांक 25-06-2021
TS Amount (lakhs) : 33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
33.00
Resanction Cost :
33.00
Tentative Cost :
33.00
Exp. Upto Last Fy : 27.36
For CFY 2024-2025
Remaining : 5.64
Demand : 5.64
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 weeks ago
25 Jun 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 12-Dec-2022
Physical Peramenters