Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 | 0 | 0 |
24W799 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO No- 035(1)/35 (1) /2021-01/2002
TS Amount (lakhs) : 407.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
407.53
Resanction Cost :
407.53
Tentative Cost :
407.53
Exp. Upto Last Fy : 407.35
For CFY 2024-2025
Remaining : 0.18
Demand : 12.91
Allotment : 12.91
Exp in CFY : 0.00
Total Up to Date Exp : 407.35
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
19 Jul 2021
Tentative Completion date:
6 months 2 weeks ago
30 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भवन कार्य पूर्ण, दायित्व शेष। -- as on 03-Jan-2024
Physical Peramenters