Work Profile Report [24W867]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO No- 495(1)/III(2)/22-69(MLA)/2017 TC-1 Date 07-01-2022
TS Amount (lakhs) : 39.14 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.14
Resanction Cost :
39.14
Tentative Cost :
39.14
Exp. Upto Last Fy :
44.67
For CFY 2025-2026
Remaining :
-5.53
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
44.67
Construction Started
Sanction on : 3 years 8 months ago
07 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 2 years 6 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सी0टी0एस0 पूर्ण। जी-3 का कार्य पूर्ण। शेष कार्य प्रगति में। -- as on 29-Aug-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand