Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.9 | 3.9 | 3.000 | 0.9 | 0.900 | 0.000 |
24W934 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 58805 दि0 24-08-2023
TS Amount (lakhs) : 84.66 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.66
Resanction Cost :
84.66
Tentative Cost :
84.66
Exp. Upto Last Fy : 35.50
For CFY 2024-2025
Remaining : 49.16
Demand : 57.04
Allotment : 35.01
Exp in CFY : 17.71
Total Up to Date Exp : 53.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 95 %
Sanction on :
10 months 3 weeks ago
25 Aug 2023
Tentative Completion date:
6 days 18 hours from now
24 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 पूर्ण पटरी प्रगति में। -- as on 10-May-2024
Physical Peramenters