Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.08 | 4.08 | 3.000 | 1.08 | 1.080 | 0.000 |
24W939 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 58805 दि0 24-08-2023
TS Amount (lakhs) : 88.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.61
Resanction Cost :
88.61
Tentative Cost :
88.61
Exp. Upto Last Fy : 27.81
For CFY 2024-2025
Remaining : 60.80
Demand : 60.80
Allotment : 40.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.81
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 95 %
Sanction on :
10 months 3 weeks ago
24 Aug 2023
Tentative Completion date:
1 week 4 days ago
06 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य प्रगति पर है। -- as on 06-Mar-2024
Physical Peramenters