Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 0.000 | 2.8 | 2.800 | 0.000 |
24W943 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 60733 दि0 11-09-2023
TS Amount (lakhs) : 60.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.87
Resanction Cost :
60.87
Tentative Cost :
60.87
Exp. Upto Last Fy : 14.40
For CFY 2024-2025
Remaining : 46.47
Demand : 46.47
Allotment : 40.00
Exp in CFY : 0.00
Total Up to Date Exp : 14.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
10 months 6 days ago
11 Sep 2023
Tentative Completion date:
3 months 1 week ago
04 Apr 2024
Actual Completion Date:
3 months 1 week ago
04 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024