Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.02 | 4.02 | 0.000 | 4.02 | 4.020 | 0.000 |
24W945 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 60733 दि0 11-09-2023
TS Amount (lakhs) : 87.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
87.34
Resanction Cost :
87.34
Tentative Cost :
87.34
Exp. Upto Last Fy : 14.45
For CFY 2024-2025
Remaining : 72.89
Demand : 72.89
Allotment : 22.30
Exp in CFY : 11.85
Total Up to Date Exp : 26.30
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 85 %
Sanction on :
10 months 6 days ago
11 Sep 2023
Tentative Completion date:
2 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी-3 पूर्ण। पी0सी0 प्रगति पर है। -- as on 01-Jun-2024
Physical Peramenters