Work Profile Report [24W946]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली संख्या 54280 लोक निर्माण अनुभाग 2 - दि0 03-10-2023
TS Amount (lakhs) : 1564.51 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1564.51
Resanction Cost :
1564.51
Tentative Cost :
1564.51
Exp. Upto Last Fy :
640.48
For CFY 2024-2025
Remaining :
924.03
Demand :
751.00
Allotment :
794.56
Exp in CFY :
739.10
Total Up to Date Exp :
1,379.58
Construction Started
Sanction on : 1 year 1 month ago
03 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
94 %
Tentative Completion date on : 2 weeks 6 days from now
14 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1800 मी0 नाली पूर्ण। 11.00 कि0मी0 लम्बाई में डी0बी0एम0, बी0सी0 पूर्ण। शेष कार्य प्रगति पर। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: