Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
24W951 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 फाईल संख्या - 58765 दि0 10-10-2023
TS Amount (lakhs) : 29.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.58
Resanction Cost :
29.58
Tentative Cost :
29.58
Exp. Upto Last Fy : 10.99
For CFY 2024-2025
Remaining : 18.59
Demand : 18.59
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 100 %
Sanction on :
9 months 1 week ago
10 Oct 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024
Physical Peramenters