Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
24W952 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
218.13
Resanction Cost :
218.13
Tentative Cost :
218.13
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 218.03
Demand : 218.03
Allotment : 51.80
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
7 months 4 weeks from now
15 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मिट्टी पूर्ण। जी0एस0बी0 पूर्ण। जी-2 कार्य प्रगति में। -- as on 12-Mar-2024
Physical Peramenters