Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.600 | 0.2 | 0.200 | 0.000 |
24W953 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 47.11 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.11
Resanction Cost :
47.11
Tentative Cost :
47.11
Exp. Upto Last Fy : 28.26
For CFY 2024-2025
Remaining : 18.85
Demand : 18.85
Allotment : 8.25
Exp in CFY : 8.25
Total Up to Date Exp : 36.51
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024