Work Profile Report [24W953]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 47.11 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.11
Resanction Cost :
47.11
Tentative Cost :
47.11
Exp. Upto Last Fy :
32.23
For CFY 2024-2025
Remaining :
14.88
Demand :
18.85
Allotment :
14.88
Exp in CFY :
8.25
Total Up to Date Exp :
40.48
Work completed
Sanction on : 1 year 1 month ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
31 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: