Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
24W954 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 96.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.29
Resanction Cost :
96.29
Tentative Cost :
96.29
Exp. Upto Last Fy : 32.04
For CFY 2024-2025
Remaining : 64.25
Demand : 64.25
Allotment : 56.46
Exp in CFY : 51.17
Total Up to Date Exp : 83.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
1 month 4 weeks ago
18 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 27-Jun-2024
Physical Peramenters