Work Profile Report [24W956]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 34.34 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
34.34
Resanction Cost :
34.34
Tentative Cost :
34.34
Exp. Upto Last Fy :
0.09
For CFY 2024-2025
Remaining :
34.25
Demand :
34.24
Allotment :
34.00
Exp in CFY :
26.65
Total Up to Date Exp :
26.74
Work completed
Sanction on : 1 year 1 month ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 06-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: