Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.500 | 0.000 |
24W956 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 58769 दि0 22-11-2023
TS Amount (lakhs) : 34.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.34
Resanction Cost :
34.34
Tentative Cost :
34.34
Exp. Upto Last Fy : 0.09
For CFY 2024-2025
Remaining : 34.25
Demand : 34.24
Allotment : 20.00
Exp in CFY : 18.00
Total Up to Date Exp : 18.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 80 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी-3 का कार्य पूर्ण। इन्टर लौकिंग टाईल का कार्य प्रगति में। -- as on 29-Jun-2024
Physical Peramenters