Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.7 | 2.7 | 2.000 | 0.7 | 0.700 | 0.000 |
24W959 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 79.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
79.38
Resanction Cost :
79.38
Tentative Cost :
79.38
Exp. Upto Last Fy : 60.10
For CFY 2024-2025
Remaining : 19.28
Demand : 19.28
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 60.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
7 months 3 weeks ago
24 Nov 2023
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 प्रगति पर है। -- as on 16-May-2024
Physical Peramenters