Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.000 | 1.2 | 1.200 | 0.000 |
24W960 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.97
Resanction Cost :
42.97
Tentative Cost :
42.97
Exp. Upto Last Fy : 15.11
For CFY 2024-2025
Remaining : 27.86
Demand : 27.86
Allotment : 8.78
Exp in CFY : 11.18
Total Up to Date Exp : 26.29
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
7 months 3 weeks ago
24 Nov 2023
Tentative Completion date:
2 months 4 weeks from now
15 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Physical Peramenters