Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
24W962 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0फाईल संख्या 59975 दि0 24-11-2023
TS Amount (lakhs) : 68.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
68.39
Resanction Cost :
68.39
Tentative Cost :
68.39
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 68.39
Demand : 68.39
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 50 %
Sanction on :
7 months 3 weeks ago
24 Nov 2023
Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी- 3 का कार्य प्रगति पर है। -- as on 16-May-2024