Work Profile Report [24W969]

जिला योजना वर्ष 2023-24 में ग्रामसभा श्रीपुर बिछुवा मझरा से गज्जर की ओर मोटर मार्ग का पुनः निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : DM Udham singh Order No. 1539/Jila Yojana-35/Finencial administration/ P.W.D/2023-24

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

32.00

Resanction Cost :

32.00

Tentative Cost :

32.00

Exp. Upto Last Fy :

11.58

For CFY 2024-2025

Remaining :

20.42

Demand :

20.42

Allotment :

18.00

Exp in CFY :

11.14

Total Up to Date Exp :

22.72

Work completed

Sanction on : 11 months 1 week ago

13 Dec 2023

Physical Progress:

At start of FY 2024-2025 :

5 %

Up to Date :

100 %

Tentative Completion date on : 3 months 2 days ago

21 Aug 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1.2
1.2
0.200
1
1.000
0.000

Remark

view all

कार्य पूर्ण। दायित्व शेष। -- as on 10-Sep-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand