Work Profile Report [24W970]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : DM Udham singh Order No. 1539/Jila Yojana-35/Finencial administration/ P.W.D/2023-24
TS Amount (lakhs) : 40 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
3.36
For CFY 2024-2025
Remaining :
36.64
Demand :
36.64
Allotment :
30.00
Exp in CFY :
30.00
Total Up to Date Exp :
33.36
Construction Started
Sanction on : 1 year 1 week ago
13 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
85 %
Tentative Completion date on : 2 months 2 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 पूर्ण। पटरी प्रगति में। -- as on 19-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: