Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.1 | 0.1 | 0.000 | 0.1 | 0.100 | 0.000 |
24W972 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : DM Udham singh Order No. 1539/Jila Yojana-35/Finencial administration/ P.W.D/2023-24
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 10.00
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
7 months 4 days ago
13 Dec 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्फेस ड्रैसिंग का कार्य प्रगति पर है। -- as on 16-May-2024
Physical Peramenters