Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.95 | 0.95 | 0.100 | 0.85 | 0.850 | 0.000 |
24W979 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन ई-फाईल संख्या 64081 दि0 01-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.54
Resanction Cost :
32.54
Tentative Cost :
32.54
Exp. Upto Last Fy : 12.62
For CFY 2024-2025
Remaining : 19.92
Demand : 19.92
Allotment : 12.54
Exp in CFY : 9.73
Total Up to Date Exp : 22.35
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 80 %
Sanction on :
5 months 2 weeks ago
01 Feb 2024
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी-2 पूर्ण। पी0सी0 प्रगति पर है। -- as on 16-May-2024
Physical Peramenters