Work Profile Report [25W1061]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 932/।।।(2)/21-64(एम0एल0ए0) /2017 टी0सी0 ।।। दिनांक 30.3.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
93.21
Resanction Cost :
93.21
Tentative Cost :
93.21
Exp. Upto Last Fy :
82.91
For CFY 2024-2025
Remaining :
10.30
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
82.91
Construction Started
Sanction on : 3 years 8 months ago
30 Mar 2021
Physical Progress:
At start of FY 2024-2025 :
1 %
Up to Date :
50 %
Tentative Completion date on : 1 year 9 months ago
15 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डब्लू0एम0एम0 का कार्य पूर्ण शेष प्रगति में। -- as on 21-Jun-2022