Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.1 | 2.1 | 2.1 | 0 |
Closed Work 25W1064 :
Administrative Approval Detail : शा0सं0 1428(।)/।।।(2)/21-62(एम0एल0ए0)/2017 दिनांक 2.6.2021
TS Amount (lakhs) : 81.23 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.23
Resanction Cost :
81.23
Tentative Cost :
81.23
Exp. Upto Last Fy : 76.84
For CFY 2024-2025
Remaining : 4.39
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 76.84
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 65 %
Sanction on :
3 years 1 month ago
02 Jun 2021
Tentative Completion date:
1 year 4 months ago
15 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.50 किमी0 में डब्लू0एम0एम0 का कार्य पूर्ण शेष प्रगति पर। -- as on 14-Nov-2022
Physical Peramenters