Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 2.800 | 0 | 0.000 | 0.000 |
25W1079 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 693/जि0यो0/लो0नि0विभाग/2021-22 दिनांक 25.6.2021
TS Amount (lakhs) : 90 Lacs
Financial Detail
Sanction Cost : 90.00 Lacs
Resanction Cost : 90.00 Lacs
Exp. Upto Last Fy : 70.30 Lacs
For CFY 2024-2025
Remaining : 19.70 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 70.30 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
25 Jun 2021
Tentative Completion date:
6 months 3 weeks ago
23 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 13-Feb-2024