Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 2.800 | 0 | 0.000 | 0.000 |
25W1079 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 693/जि0यो0/लो0नि0विभाग/2021-22 दिनांक 25.6.2021
TS Amount (lakhs) : 90 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
90.00
Resanction Cost :
90.00
Tentative Cost :
90.00
Exp. Upto Last Fy : 70.30
For CFY 2024-2025
Remaining : 19.70
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 70.30
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 weeks ago
25 Jun 2021
Tentative Completion date:
8 months 3 weeks ago
23 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 13-Feb-2024
Physical Peramenters