Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.226 | 14.226 | 14.226 | 0 | 0.000 | 0.000 |
25W1109 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /106915 /2023 (ई0 फाईल सं0 48224) दि0 16.3.23
TS Amount (lakhs) : 658.86 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
658.86
Resanction Cost :
658.86
Tentative Cost :
658.86
Exp. Upto Last Fy : 602.88
For CFY 2024-2025
Remaining : 55.98
Demand : 50.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 602.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
16 Mar 2023
Tentative Completion date:
1 year 2 months ago
19 Apr 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 09-Apr-2023
Physical Peramenters