Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
25W1110 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /110015 /2023 (ई0 फाईल सं0 28686) दि0 25.3.23
TS Amount (lakhs) : 518.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
518.26
Resanction Cost :
518.26
Tentative Cost :
518.26
Exp. Upto Last Fy : 348.07
For CFY 2024-2025
Remaining : 170.19
Demand : 170.00
Allotment : 155.00
Exp in CFY : 122.53
Total Up to Date Exp : 470.60
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
25 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
30 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-Jun-2024
Physical Peramenters