Work Profile Report [25W1111]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /110015 /2023 (ई0 फाईल सं0 28686) दि0 25.3.23
TS Amount (lakhs) : 553.25 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
553.25
Resanction Cost :
553.25
Tentative Cost :
447.25
Saving
106.00
Exp. Upto Last Fy :
192.23
For CFY 2024-2025
Remaining :
361.02
Demand :
300.00
Allotment :
243.59
Exp in CFY :
229.78
Total Up to Date Exp :
422.01
Work completed
Sanction on : 1 year 7 months ago
25 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
03 Jul 2024
Actual Completion Date : 4 months 3 weeks ago
30 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: