Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.7 | 2.7 | 0.000 | 2.7 | 2.700 | 0.000 |
25W1111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /110015 /2023 (ई0 फाईल सं0 28686) दि0 25.3.23
TS Amount (lakhs) : 553.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
553.25
Resanction Cost :
553.25
Tentative Cost :
553.25
Exp. Upto Last Fy : 192.23
For CFY 2024-2025
Remaining : 361.02
Demand : 300.00
Allotment : 200.00
Exp in CFY : 138.64
Total Up to Date Exp : 330.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
25 Mar 2023
Tentative Completion date:
2 weeks 5 hours ago
03 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-Jun-2024
Physical Peramenters