Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.7 | 2.7 | 0.000 | 2.7 | 2.700 | 0.000 |
25W1111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /110015 /2023 (ई0 फाईल सं0 28686) दि0 25.3.23
TS Amount (lakhs) : 553.25 Lacs
Financial Detail
Sanction Cost : 553.25 Lacs
Resanction Cost : 553.25 Lacs
Exp. Upto Last Fy : 192.23 Lacs
For CFY 2024-2025
Remaining : 361.02 Lacs
Demand : 300.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 192.23 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
1 year 1 month ago
25 Mar 2023
Tentative Completion date:
1 month 2 weeks from now
03 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0बी0एम0 प्रथम लेयर का कार्य पूर्ण शेष कार्य प्रगति में। -- as on 01-Nov-2023