Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.91 | 0.91 | 0.000 | 0.91 | 0.910 | 0.000 |
25W1113 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /105444 /2023 (ई0 फाईल सं0 47605) दि0 13.3.23
TS Amount (lakhs) : 23.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23.25
Resanction Cost :
23.25
Tentative Cost :
23.25
Exp. Upto Last Fy : 11.84
For CFY 2024-2025
Remaining : 11.41
Demand : 8.00
Allotment : 8.00
Exp in CFY : 0.17
Total Up to Date Exp : 12.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
1 year 4 months ago
13 Mar 2023
Tentative Completion date:
3 months 18 hours from now
18 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0बी0एम0 का कार्य पूर्ण शेष कार्य प्रगति में। -- as on 14-Jul-2023