Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.600 | 0.000 |
25W1119 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /108217 /2023 (ई0 फाईल सं0 29156) दि0 21.03.23
TS Amount (lakhs) : 68.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
68.14
Resanction Cost :
68.14
Tentative Cost :
68.14
Exp. Upto Last Fy : 33.40
For CFY 2024-2025
Remaining : 34.74
Demand : 25.00
Allotment : 25.00
Exp in CFY : 23.39
Total Up to Date Exp : 56.79
Work completed
Physical Progress:
At start of FY 2024-2025 : 78 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
20 Mar 2023
Tentative Completion date:
4 months 6 days ago
11 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-May-2024
Physical Peramenters