Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 0.000 | 1.7 | 1.700 | 0.000 |
25W1121 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /104610 /2023 (ई0 फाईल सं0 35889) दि0 6.3.23
TS Amount (lakhs) : 90.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
90.15
Resanction Cost :
90.15
Tentative Cost :
90.15
Exp. Upto Last Fy : 18.32
For CFY 2024-2025
Remaining : 71.83
Demand : 50.00
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.32
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
1 year 4 months ago
06 Mar 2023
Tentative Completion date:
2 months 3 weeks from now
11 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0एम0एम0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters