Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.1 | 1.1 | 0.900 | 0.2 | 0.200 | 0.000 |
25W1122 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /104610 /2023 (ई0 फाईल सं0 35889) दि0 6.3.23
TS Amount (lakhs) : 45.74 Lacs
Financial Detail
Sanction Cost : 45.74 Lacs
Resanction Cost : 45.74 Lacs
Exp. Upto Last Fy : 34.98 Lacs
For CFY 2024-2025
Remaining : 10.76 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 34.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
06 Mar 2023
Tentative Completion date:
3 months 1 day ago
18 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
900 मी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 11-Apr-2024
Physical Peramenters