Work Profile Report [25W1125]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /104610 /2023 (ई0 फाईल सं0 35889) दि0 6.3.23
TS Amount (lakhs) : 53.43 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.43
Resanction Cost :
53.43
Tentative Cost :
53.43
Exp. Upto Last Fy :
40.66
For CFY 2024-2025
Remaining :
12.77
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
40.66
Work completed
Sanction on : 1 year 9 months ago
06 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 10 months 6 days ago
21 Feb 2024
Actual Completion Date : 1 year 1 month ago
15 Nov 2023
Physical Linear Components
Remark
कार्य पूर्ण -- as on 11-Apr-2024