Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.78 | 0.78 | 0.000 | 0.78 | 0.580 | 0.000 |
25W1128 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /111699 /2023 (ई0 फाईल सं0 47605) दि0 31.3.23
TS Amount (lakhs) : 33.88 Lacs
Financial Detail
Sanction Cost : 33.88 Lacs
Resanction Cost : 33.88 Lacs
Exp. Upto Last Fy : 22.17 Lacs
For CFY 2024-2025
Remaining : 11.71 Lacs
Demand : 11.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 22.17 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
2 months 1 week ago
06 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
200 मी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters