Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.000 | 0.000 |
25W1129 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /111699 /2023 (ई0 फाईल सं0 47605) दि0 31.3.23
TS Amount (lakhs) : 89.9 Lacs
Financial Detail
Sanction Cost : 89.90 Lacs
Resanction Cost : 89.90 Lacs
Exp. Upto Last Fy : 72.57 Lacs
For CFY 2024-2025
Remaining : 17.33 Lacs
Demand : 16.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 72.57 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
2 months 3 days ago
16 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
500 मी0 लम्बाई में कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters