Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.000 |
25W1136 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /36334 /2023 (ई0 फाईल सं0 47605) दि0 10.07.2023
TS Amount (lakhs) : 28.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.87
Resanction Cost :
28.87
Tentative Cost :
28.87
Exp. Upto Last Fy : 11.57
For CFY 2024-2025
Remaining : 17.30
Demand : 17.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.57
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 week ago
10 Jul 2023
Tentative Completion date:
2 months 1 day from now
19 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण शेष कार्य प्रगति में -- as on 11-Apr-2024
Physical Peramenters