Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.000 |
25W1139 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /36334 /2023 (ई0 फाईल सं0 47605) दि0 10.07.2023
TS Amount (lakhs) : 25.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.38
Resanction Cost :
25.38
Tentative Cost :
25.38
Exp. Upto Last Fy : 4.26
For CFY 2024-2025
Remaining : 21.12
Demand : 16.00
Allotment : 16.00
Exp in CFY : 15.40
Total Up to Date Exp : 19.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 78 %
Up to Date : 100 %
Sanction on :
1 year 1 week ago
10 Jul 2023
Tentative Completion date:
4 months 5 days ago
12 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष -- as on 05-Jun-2024
Physical Peramenters