Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
25W1140 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 24.74 Lacs
Financial Detail
Sanction Cost : 24.74 Lacs
Resanction Cost : 24.74 Lacs
Exp. Upto Last Fy : 8.00 Lacs
For CFY 2024-2025
Remaining : 16.74 Lacs
Demand : 12.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 8.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
11 months 34 minutes ago
19 Jun 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण शेष कार्य प्रगति में। -- as on 12-Feb-2024
Physical Peramenters