Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 1.800 | 0.000 |
25W1141 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 94.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.15
Resanction Cost :
94.15
Tentative Cost :
94.15
Exp. Upto Last Fy : 64.64
For CFY 2024-2025
Remaining : 29.51
Demand : 22.00
Allotment : 20.00
Exp in CFY : 18.82
Total Up to Date Exp : 83.46
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
3 months 1 week ago
09 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-May-2024
Physical Peramenters