Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.65 | 1.65 | 0.000 | 1.65 | 1.650 | 0.000 |
25W1145 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 58.59 Lacs
Financial Detail
Sanction Cost : 58.59 Lacs
Resanction Cost : 58.59 Lacs
Exp. Upto Last Fy : 10.63 Lacs
For CFY 2024-2025
Remaining : 47.96 Lacs
Demand : 35.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 18.30 Lacs
Total Up to Date Exp : 28.93 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
10 months 54 minutes ago
19 Jul 2023
Tentative Completion date:
2 months 2 weeks ago
03 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट, नाली निर्माण आदि का कार्य पूर्ण शेष कार्य प्रगति में। -- as on 12-Feb-2024
Physical Peramenters