Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.65 | 1.65 | 0.000 | 1.65 | 1.650 | 0.000 |
25W1145 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 58.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.59
Resanction Cost :
58.59
Tentative Cost :
58.59
Exp. Upto Last Fy : 10.63
For CFY 2024-2025
Remaining : 47.96
Demand : 35.00
Allotment : 30.00
Exp in CFY : 18.74
Total Up to Date Exp : 29.37
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
1 month 2 weeks from now
03 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.20 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति में। -- as on 05-Jun-2024
Physical Peramenters