Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.000 | 0.7 | 0.700 | 0.000 |
25W1146 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /38893 /2023 (ई0 फाईल सं0 54118) दि0 19.07.2023
TS Amount (lakhs) : 21.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.63
Resanction Cost :
21.63
Tentative Cost :
21.63
Exp. Upto Last Fy : 2.71
For CFY 2024-2025
Remaining : 18.92
Demand : 12.00
Allotment : 0.00
Exp in CFY : 0.18
Total Up to Date Exp : 2.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 100 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-Jun-2024
Physical Peramenters