Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 3.500 | 0.000 |
25W1153 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /42056 /2023 (ई0 फाईल सं0 50220) दि0 31.07.2023
TS Amount (lakhs) : 176.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
176.22
Resanction Cost :
176.22
Tentative Cost :
176.22
Exp. Upto Last Fy : 144.69
For CFY 2024-2025
Remaining : 31.53
Demand : 30.00
Allotment : 20.00
Exp in CFY : 4.22
Total Up to Date Exp : 148.91
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 90 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.40 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 27-May-2024