Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.01 | 1.01 | 0.000 | 1.01 | 0.000 | 0.000 |
25W1154 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /164733 /2023 (ई0 फाईल सं0 47605) दि0 27.10.2023
TS Amount (lakhs) : 99.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
99.16
Resanction Cost :
99.16
Tentative Cost :
99.16
Exp. Upto Last Fy : 0.19
For CFY 2024-2025
Remaining : 98.97
Demand : 50.00
Allotment : 20.00
Exp in CFY : 18.61
Total Up to Date Exp : 18.81
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 40 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
2 months 3 weeks from now
09 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.65 किमी0 लम्बाई में जी0एस0बी0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters