Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.01 | 1.01 | 0.000 | 1.01 | 0.000 | 0.000 |
25W1154 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /164733 /2023 (ई0 फाईल सं0 47605) दि0 27.10.2023
TS Amount (lakhs) : 99.16 Lacs
Financial Detail
Sanction Cost : 99.16 Lacs
Resanction Cost : 99.16 Lacs
Exp. Upto Last Fy : 0.19 Lacs
For CFY 2024-2025
Remaining : 98.97 Lacs
Demand : 50.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.19 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
तटबंध निर्माण का कार्य प्रगति में। -- as on 11-Apr-2024
Physical Peramenters