Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.95 | 1.95 | 0.000 | 1.95 | 1.950 | 0.000 |
25W1155 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /167915 /2023 (ई0 फाईल सं0 56071) दि0 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
109.75
Resanction Cost :
109.75
Tentative Cost :
109.75
Exp. Upto Last Fy : 47.59
For CFY 2024-2025
Remaining : 62.16
Demand : 50.00
Allotment : 5.00
Exp in CFY : 0.48
Total Up to Date Exp : 48.07
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
2 months 3 weeks from now
10 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण शेष कार्य प्रगति में -- as on 11-Apr-2024
Physical Peramenters