Work Profile Report [25W1155]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /167915 /2023 (ई0 फाईल सं0 56071) दि0 09.11.2023
TS Amount (lakhs) : 109.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
109.75
Resanction Cost :
109.75
Tentative Cost :
100.00
Saving
9.75
Exp. Upto Last Fy :
47.59
For CFY 2024-2025
Remaining :
62.16
Demand :
50.00
Allotment :
45.00
Exp in CFY :
22.47
Total Up to Date Exp :
70.06
Construction Started
Sanction on : 1 year 2 weeks ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
90 %
Tentative Completion date on : 3 months 1 week from now
05 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: